In a power cut the whole street goes dark — except one house. That house has a hybrid inverter and a battery. This is the written version of our first video: what is inside the box, how energy moves through it, and the three numbers to understand before you buy one.
Grid-tie, off-grid and hybrid
A grid-tie inverter turns the DC from your solar panels into AC for the house and the grid. It has no battery, and it must shut down when the grid fails — so a plain grid-tie system gives you nothing in a power cut. An off-grid system never connects to the utility at all.
A hybrid inverter does both jobs. Panels, a battery, the grid and a separate backup output all connect to one box. Inside, everything meets on a shared DC bus. Each of the four “doors” has its own converter, and a controller decides, second by second, where every watt goes.
The solar door: MPPT
Panels don't have one fixed voltage. More sunlight gives more current; hotter cells give lower voltage and lose roughly 0.4–0.5 % of their power per degree. So the best operating point moves all day. The solar input runs MPPT — maximum power point tracking: a DC-DC converter keeps adjusting the panel voltage to find the point that gives the most power right now.
Every inverter also has an MPPT voltage window and a hard maximum input voltage. Panel voltage rises in the cold, so the string must stay under that maximum on the coldest morning. That is your installer's calculation, not a guess.
The battery door
The battery connects through a bidirectional converter: it charges and discharges through the same door. Many home hybrids use a 48 V battery; high-voltage systems stack modules to a few hundred volts.
At the same power, the voltage decides the current. 5 kW from a 48 V battery is about 104 A; from a 400 V battery it is about 12.5 A (power = volts × amps). That is why low-voltage battery cables and breakers are so thick. A lithium battery also talks to the inverter over a data cable (CAN or RS485), so the inverter knows its state of charge and its limits.
Making 230 V AC
The DC bus sits at a few hundred volts — above the 325 V peak of a 230 V sine wave. A full bridge of fast switches chops that DC into pulses, and a filter smooths them into a clean sine wave, 50 times a second. Run the other way, the same bridge can charge the battery from the grid.
An inverter converts power; it never makes more than the panels and battery give it. The best hybrids lose only about 3 % on the way.
Anti-islanding and zero export
When the grid fails, a grid-connected inverter must stop feeding the network. This is anti-islanding, and it protects the people repairing the line, who expect it to be dead. In South Africa (NRS 097-2-1) and in India the inverter must stop within 2 seconds.
Zero export works the other way round. A current sensor at your supply point sees power flowing out to the grid, and the inverter throttles back to exactly what the house is using. With a full battery, some solar simply isn't harvested.
What happens in a power cut
A transfer relay separates the backup output from the grid, and the inverter then makes its own voltage and frequency from solar and battery. Many hybrids switch over in about 10 milliseconds; some take seconds — check the datasheet if your computers must not reboot.
Backup power is limited, so only essential circuits go on the backup side: lights, fridge, Wi-Fi, TV, alarm. Heavy loads such as the hot water source, oven and pool pump usually stay on the grid side. And never connect the backup output to the grid.
Self-use, battery-first and time-of-use
Most hybrids offer the same three work modes. Self-use: solar feeds the house first, then charges the battery, then exports. Battery-first: the battery is charged before anything is exported. Time-of-use: you choose time slots to charge from the grid and to use the battery, to match your tariff.
kWp vs kW vs kWh
Three numbers, three jobs. kWp is the panels' rated DC output. kW is how much the inverter can run at once — a 5 kW inverter caps what can run together. kWh is how much energy the battery stores, so it sets how long you last. A bigger battery won't run more at once: a kettle, an oven and a hot water source together can easily need more than 5 kW.
The rules where you live
South Africa: register the system with your municipality or Eskom before it is installed, even if it never exports. The inverter must be type-tested to NRS 097-2-1, and the wiring needs a Certificate of Compliance under SANS 10142-1.
UK: BS 7671, and your network operator is notified under ENA G98 or applied to under G99; MCS certification for the Smart Export Guarantee. Europe: EN 50549-1 and your network operator's rules (Germany: VDE-AR-N 4105). Australia / NZ: a CEC-listed inverter, AS/NZS 4777, AS/NZS 5139 for batteries, AS/NZS 5033 for the array and AS/NZS 3000. India: the CEA connectivity regulations and a BIS-registered inverter (IS 16169 islanding test). Check the current edition of each standard with your local authority.
Safety: live panels and DC arcs
Solar panels in daylight are always live, even with the inverter switched off. And a DC arc doesn't go out by itself the way an AC arc tends to at every zero crossing. Isolators, roof work and wiring are jobs for a registered installer.
Educational only — not installation advice. Electrical, solar and battery work must be done by a registered or licensed person and meet your local rules.
Sources
US Department of Energy — Solar integration: inverters and grid services basics
Clean Energy Council (AU) — Guide to installing a household battery
Renesas — PV and battery hybrid inverter architecture
Energies 15(20):7539 — hybrid inverter topologies (MDPI)
PVEducation — Effect of temperature on solar cells
Deye SUN-3.6–6K-SG03LP1 user manual
GoodWe A-ES user manual
NRS 097-2-1:2024
City of Cape Town — Requirements for small-scale embedded generation
Eskom — Small-scale embedded generators
ENA EREC G98 Issue 2
AEMO — AS/NZS 4777.2 inverter requirements
MDPI Machines 12(2):134 — DC arc faults
Our Solar Insurance-Ready File is a fillable PDF for homes with solar panels, an inverter or a battery: what insurers commonly ask for, 7 questions to ask yours, a CoC check where every line names its clause, an equipment register, a photo log and claim-day steps. Comes with a free 8-point paperwork check.
Get the file · $9 ▶Organisers only, not legal or insurance advice: your municipality, Eskom or your insurer decides. Made with AI assistance from public sources. Sold by SortBright, a Kleinson Solutions (Pty) Ltd store.
CIRCUIT & CURRENT
Home energy and electrical, from zero to engineer. Animated.
YouTube · Calculator · Newsletter · Privacy
Explainers only — not installation advice. Electrical, solar and battery work must be done by a registered or licensed person. © Kleinson Solutions